A project manager discovered that a component on the critical path is in danger of delay due to continuous disagreements between two developers. This personality-related issue can't be resolved by the team.

What should the project manager do?

A.
Log the issue in the register and delay the development of the component.
Answers
A.
Log the issue in the register and delay the development of the component.
B.
Log the issue in the register and ask the team to make a decision by voting.
Answers
B.
Log the issue in the register and ask the team to make a decision by voting.
C.
Log the issue in the register and escalate to the human resources (HR) manager.
Answers
C.
Log the issue in the register and escalate to the human resources (HR) manager.
D.
Log the issue in the register and let the developers resolve the conflict.
Answers
D.
Log the issue in the register and let the developers resolve the conflict.
Suggested answer: C