Question 1041 - PMP discussion
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
A.
By focusing on the delivery of incremental working products to the customer
B.
By conducting daily standups to more accurately track project deliverables
C.
By reviewing burnup charts to determine the effort required against estimated earned value
D.
By scheduling iterative meetings with the product owner to improve project tracking