A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between:

- Test the product

- Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

A.
Start to start
Answers
A.
Start to start
B.
Finish to start
Answers
B.
Finish to start
C.
Finish to finish
Answers
C.
Finish to finish
D.
Start to finish
Answers
D.
Start to finish
Suggested answer: B