Question 1087 - PMP discussion
A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
A.
Organize a new schedule framing meeting with the critical stakeholder to obtain input.
B.
Discuss with the project sponsor and create a new project schedule.
C.
Analyze the root cause of the issue and update the communications management plan.
D.
Reach out to the project sponsor and request additional resources.