Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.

What should the project leader do?

A.
Tell the team that the event will be handled at the end of the project due to current financial constraints
Answers
A.
Tell the team that the event will be handled at the end of the project due to current financial constraints
B.
Bypass the event because the team members' seniority is enough to engage without further activities
Answers
B.
Bypass the event because the team members' seniority is enough to engage without further activities
C.
Explain the financial constraint and ask each team member to pay their own share for the event
Answers
C.
Explain the financial constraint and ask each team member to pay their own share for the event
D.
Use the office facilities and support to organize an interactive event for the team members inhouse
Answers
D.
Use the office facilities and support to organize an interactive event for the team members inhouse
Suggested answer: D