Question 1095 - PMP discussion
Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
A.
Shift those key members and assign them to another project.
B.
Cancel the meeting series until the marketing team provides a solution.
C.
Consult the project team and discuss the key team members' availability.
D.
Consult the resource management plan and escalate to the sponsor.
Your answer: