A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know how frequently the risks are being reviewed.

Which document project manager should check first?

Risk management plan
Risk management plan
Risk register
Risk register
Issue log
Issue log
Risk report
Risk report
Suggested answer: B
asked 23/09/2024
Sebasteen Lawrance
43 questions

Question 1092

Report
Export
Collapse

A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested candidates, including former suppliers and suppliers recommended by the sponsor.

What should the project manager do in this situation?

Evaluate suppliers who have worked successfully with the company before
Evaluate suppliers who have worked successfully with the company before
Request the contracting area take charge of the supplier evaluation process
Request the contracting area take charge of the supplier evaluation process
Prioritize evaluation of the suppliers recommended by the sponsor
Prioritize evaluation of the suppliers recommended by the sponsor
Evaluate the suppliers based on their experience and skills in similar projects
Evaluate the suppliers based on their experience and skills in similar projects
Suggested answer: D
asked 23/09/2024
Elvis WANDJI NGASSA
43 questions

Question 1093

Report
Export
Collapse

A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability to perform a what-if analysis in the tool based on the customer demand and forecast.

What should the project manager do next?

Revise the project schedule and budget based on the additional scope, and review with the team.
Revise the project schedule and budget based on the additional scope, and review with the team.
Include the new capability to the product backlog and continue activities based on the current plan.
Include the new capability to the product backlog and continue activities based on the current plan.
Perform an impact analysis on the schedule and budget based on the additional scope.
Perform an impact analysis on the schedule and budget based on the additional scope.
Analyze and negotiate with the executive steering committee regarding this new request.
Analyze and negotiate with the executive steering committee regarding this new request.
Suggested answer: C
asked 23/09/2024
Trang Anna
38 questions

Question 1094

Report
Export
Collapse

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Communicate with the industry's regulatory authority to grant the company an exception.
Communicate with the industry's regulatory authority to grant the company an exception.
Hire a third party who is an expert on the industry's regulations to work out the details.
Hire a third party who is an expert on the industry's regulations to work out the details.
Escalate the issue to the company's CEO who has experience with the regulations.
Escalate the issue to the company's CEO who has experience with the regulations.
Comply with the regulatory requirements and work to compress the project schedule.
Comply with the regulatory requirements and work to compress the project schedule.
Suggested answer: D
asked 23/09/2024
Lakshmana Mittadoddi
39 questions

Question 1095

Report
Export
Collapse

Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.

What should the project manager do?

Shift those key members and assign them to another project.
Shift those key members and assign them to another project.
Cancel the meeting series until the marketing team provides a solution.
Cancel the meeting series until the marketing team provides a solution.
Consult the project team and discuss the key team members' availability.
Consult the project team and discuss the key team members' availability.
Consult the resource management plan and escalate to the sponsor.
Consult the resource management plan and escalate to the sponsor.
Suggested answer: D
asked 23/09/2024
Eric Hebert
35 questions

Question 1096

Report
Export
Collapse

At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.

What should the project manager do?

Ask the product owner to provide more details in the standup.
Ask the product owner to provide more details in the standup.
Organize a workshop after the standup to assess the impact.
Organize a workshop after the standup to assess the impact.
Prepare a budget change request for additional resources.
Prepare a budget change request for additional resources.
Create a new product backlog item for the next sprint planning.
Create a new product backlog item for the next sprint planning.
Suggested answer: B
asked 23/09/2024
PKE Holding AG Leitgeb
33 questions

Question 1097

Report
Export
Collapse

A product owner is trying to understand how many of the user stones have been completed within a 2-week sprint. How should the project manager approach this situation?

Use retrospectives to deliver the finished products.
Use retrospectives to deliver the finished products.
Invite the product owner to regular standup meetings.
Invite the product owner to regular standup meetings.
Have a face-to-face conversation with the product owner.
Have a face-to-face conversation with the product owner.
Share the burndown chart with the product owner.
Share the burndown chart with the product owner.
Suggested answer: D
asked 23/09/2024
Ioana Mihaila
49 questions

Question 1098

Report
Export
Collapse

A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcome should be.

What should the project manager do to resolve this?

Check to ensure the project outcome aligns with the project charter and statement of work (SOW).
Check to ensure the project outcome aligns with the project charter and statement of work (SOW).
Invite the project sponsor to the sprint review to provide clarity on the sprint outcome.
Invite the project sponsor to the sprint review to provide clarity on the sprint outcome.
Ask the product owner to address the concerns about the project outcome during the sprint retrospective.
Ask the product owner to address the concerns about the project outcome during the sprint retrospective.
Schedule a meeting with the stakeholders to determine a consensus regarding the outcome.
Schedule a meeting with the stakeholders to determine a consensus regarding the outcome.
Suggested answer: A
asked 23/09/2024
Jucelino Pinheiro de Andrade da Silva
42 questions

Question 1099

Report
Export
Collapse

A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company's operations support team. However, many new members have just been added to the operations support team who are not familiar with the project and the project's acceptance is now at risk.

What should the project manager do to mitigate this transition risk?

Request the steering committee to reevaluate the feasibility of transitioning and closing the project given the personnel changes on the operations support team.
Request the steering committee to reevaluate the feasibility of transitioning and closing the project given the personnel changes on the operations support team.
Request the steering committee to train only the selected operations team members who are familiar with the project and then train the new team members separately.
Request the steering committee to train only the selected operations team members who are familiar with the project and then train the new team members separately.
Request the steering committee to exclude the new team members during the transition and train the new members after the planned transition is completed
Request the steering committee to exclude the new team members during the transition and train the new members after the planned transition is completed
Request the steering committee to authorize an early project deployment (i.e., a "beta" transition release) and engage the operations support team in the early release.
Request the steering committee to authorize an early project deployment (i.e., a "beta" transition release) and engage the operations support team in the early release.
Suggested answer: D
asked 23/09/2024
FELIPE VILLAGOMEZ CARDENAS VILLAGOMEZ
42 questions

Question 1100

Report
Export
Collapse

A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During the user story creation phase, the product owner met with multiple stakeholders who had different opinions about the requirements.

How should the project manager address this situation?

Ask the product owner to create the backlog.
Ask the product owner to create the backlog.
Use a voting system for stakeholders.
Use a voting system for stakeholders.
Perform a stakeholder identification analysis.
Perform a stakeholder identification analysis.
Limit the participation from stakeholders.
Limit the participation from stakeholders.
Suggested answer: B