PMI PMP Practice Test - Questions Answers, Page 111
List of questions
Related questions
A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.
What should the project manager do to improve overall team performance?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives.
The project runs into further delays as the project manager is ramping up on the project. The stakeholders are unhappy and ask senior management to replace the project manager.
How should the project manager approach this situation?
A project manager has been assigned to a new project. The project schedule is extremely short. During an iteration review meeting. the key stakeholder mentions that they are experiencing some inefficiencies in their work processes.
What should the project manager do?
At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week. the project team realizes that the activities were executed in the wrong way because each team member had a different understanding. These misunderstandings have caused a delay in the project.
Which of the following actions should the project manager take to avoid this situation in the future?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
A project lead is managing a project in the execution phase. A new product owner was assigned and the project lead had their first meeting with the new product owner. During the meeting, the new product owner indicated the scope of the first release needs to be changed.
What should the project lead ask the product owner to do first?
A project manager is working on an international effort that involves a project team located on four different continents. The project team is extremely proud of the progress they have made on a recent iteration of the project. However, senior stakeholders unfamiliar with the project's progress are concerned that the project may be unsuccessful.
What should the project manager do to help mitigate the stakeholders' concerns?
During user acceptance testing, a project sponsor asks the project manager to add a couple of features. To meet the firm go-live date, the project team will need to work overtime.
What should the project manager do?
In a daily standup, the project lead notices that one of the senior developers is reassigning some of the easy backlog items to other team members, arguing that it is more efficient for the senior developers to work on complex items. What should the project lead do?
A project team is working remotely on a project with tight deadlines. In the middle of the project, a team member is replaced with an individual who is new to the company. The document repository is available to review, but since the project is quite complex it could take time to understand the details related to the new team member's responsibilities.
What should the project manager do?
Question