A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.

When should the risks be reviewed to ensure alignment between the project team and the stakeholders?

A.
During each steering committee meeting
A.
During each steering committee meeting
Answers
B.
During the retrospectives
B.
During the retrospectives
Answers
C.
During the risk register update
C.
During the risk register update
Answers
D.
During each iteration and review
D.
During each iteration and review
Answers
Suggested answer: D

A project is in the planning phase. The project manager notices that the available engineers do not have the required skills. Since outsourcing is not an option for this project, the project manager asks human resources (HR) to hire or assign engineers with the required skills.

However, the company cannot afford this at the moment.

What should the project manager do first?

A.
Introduce a mentoring program to facilitate knowledge sharing.
A.
Introduce a mentoring program to facilitate knowledge sharing.
Answers
B.
Change the scope to include only the work that the team is qualified to do.
B.
Change the scope to include only the work that the team is qualified to do.
Answers
C.
Add extra time for training during the course of the project.
C.
Add extra time for training during the course of the project.
Answers
D.
Use the management reserve to obtain the needed resources.
D.
Use the management reserve to obtain the needed resources.
Answers
Suggested answer: C

DRAG DROP

Drag the interpersonal skill on the left to the correct scenario on the right.


Question 1083
Correct answer: Question 1083

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to know about the deliverable.

What should the project manager do next?

A.
Check if these stakeholders attend regular project meetings.
A.
Check if these stakeholders attend regular project meetings.
Answers
B.
Meet with these stakeholders to review the project charter.
B.
Meet with these stakeholders to review the project charter.
Answers
C.
Review the project charter to validate this claim
C.
Review the project charter to validate this claim
Answers
D.
Validate if the project charter changed from the original one.
D.
Validate if the project charter changed from the original one.
Answers
Suggested answer: B

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

A.
Work on the backlog activities with fewer story points.
A.
Work on the backlog activities with fewer story points.
Answers
B.
Ask for more resources to clear the backlog activities.
B.
Ask for more resources to clear the backlog activities.
Answers
C.
Prioritize which backlog activities should be kept.
C.
Prioritize which backlog activities should be kept.
Answers
D.
Assign an owner for each backlog activity and track progress
D.
Assign an owner for each backlog activity and track progress
Answers
Suggested answer: C

Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.

What should the project leader do?

A.
Tell the team that the event will be handled at the end of the project due to current financial constraints
A.
Tell the team that the event will be handled at the end of the project due to current financial constraints
Answers
B.
Bypass the event because the team members' seniority is enough to engage without further activities
B.
Bypass the event because the team members' seniority is enough to engage without further activities
Answers
C.
Explain the financial constraint and ask each team member to pay their own share for the event
C.
Explain the financial constraint and ask each team member to pay their own share for the event
Answers
D.
Use the office facilities and support to organize an interactive event for the team members inhouse
D.
Use the office facilities and support to organize an interactive event for the team members inhouse
Answers
Suggested answer: D

A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.

What should the project manager do first?

A.
Organize a new schedule framing meeting with the critical stakeholder to obtain input.
A.
Organize a new schedule framing meeting with the critical stakeholder to obtain input.
Answers
B.
Discuss with the project sponsor and create a new project schedule.
B.
Discuss with the project sponsor and create a new project schedule.
Answers
C.
Analyze the root cause of the issue and update the communications management plan.
C.
Analyze the root cause of the issue and update the communications management plan.
Answers
D.
Reach out to the project sponsor and request additional resources.
D.
Reach out to the project sponsor and request additional resources.
Answers
Suggested answer: A

A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.
Send an email to all stakeholders.
A.
Send an email to all stakeholders.
Answers
B.
Refer to the stakeholder engagement plan.
B.
Refer to the stakeholder engagement plan.
Answers
C.
Set up a conference call for all stakeholders.
C.
Set up a conference call for all stakeholders.
Answers
D.
Refer to the communications management plan.
D.
Refer to the communications management plan.
Answers
Suggested answer: D

A project team is in the planning phase of a product migration project. The project manager schedules a meeting with the project team, telecommunications team, and the department leaders with group product accounts. The purpose of the meeting is to determine the project timeline based on how much content needs to be transferred to or created in the new system and the processing procedures and time frames.

Who should the project manager also invite to the meeting?

A.
Representative from the provisioning team
A.
Representative from the provisioning team
Answers
B.
Representative from the network team
B.
Representative from the network team
Answers
C.
Representative from the reimbursement team
C.
Representative from the reimbursement team
Answers
D.
Representative from the service desk team
D.
Representative from the service desk team
Answers
Suggested answer: B

A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support at project completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.

What should the project manager do to resolve the conflict?

A.
Seek to understand the project stakeholders' needs in an effort to support the new technology.
A.
Seek to understand the project stakeholders' needs in an effort to support the new technology.
Answers
B.
Communicate the project's progress to the stakeholders and promote the new technology.
B.
Communicate the project's progress to the stakeholders and promote the new technology.
Answers
C.
Maintain and adhere to project plans to ensure the project delivers successful outcomes.
C.
Maintain and adhere to project plans to ensure the project delivers successful outcomes.
Answers
D.
Acknowledge the lack of approval and focus on a resolution that will benefit the customer.
D.
Acknowledge the lack of approval and focus on a resolution that will benefit the customer.
Answers
Suggested answer: D