PMI PMP Practice Test - Questions Answers, Page 108
List of questions
Related questions
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
DRAG DROP
A new project manager for an agile project is reviewing, with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the appropriate role on the right.
DRAG DROP
The team has reported the following impediments at the daily standup meeting. Drag each impediment on the left to the action that the project manager needs to take on the right.
A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.
What should the project manager do?
A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly.
What should the senior project manager do?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will not get the expected bonus if they do not finish on time.
What should the project manager do next?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.
What should the project manager do?
A project manager is in the middle or handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part or the project are being moved to another priority project.
What should the project manager do?
Company A has a culture of adhering to policies and procedures. A project manager is applying an agile approach to their in-house software development project, but even with training, they are still unable to deliver efficiently.
What should the project manager do first to improve this situation?
Question