ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 108

List of questions

Question 1071

Report Export Collapse

A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 1072

Report Export Collapse

DRAG DROP

A new project manager for an agile project is reviewing, with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the appropriate role on the right.


Become a Premium Member for full access
  Unlock Premium Member

Question 1073

Report Export Collapse

DRAG DROP

The team has reported the following impediments at the daily standup meeting. Drag each impediment on the left to the action that the project manager needs to take on the right.


Become a Premium Member for full access
  Unlock Premium Member

Question 1074

Report Export Collapse

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1075

Report Export Collapse

A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly.

What should the senior project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1076

Report Export Collapse

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 1077

Report Export Collapse

A project manager noticed that a team member has been struggling with some tasks, which may ultimately impact the completion date. Team morale is low because they will not get the expected bonus if they do not finish on time.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1078

Report Export Collapse

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1079

Report Export Collapse

A project manager is in the middle or handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part or the project are being moved to another priority project.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1080

Report Export Collapse

Company A has a culture of adhering to policies and procedures. A project manager is applying an agile approach to their in-house software development project, but even with training, they are still unable to deliver efficiently.

What should the project manager do first to improve this situation?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions