PMI PMP Practice Test - Questions Answers, Page 106

List of questions
Question 1051

A project has been running successfully for 2 months. At a regular project meeting, the team raises several potential obstacles to future progress. The obstacles include vendor delivery performance, technical performance of a subsystem, and conflict with another division of the organization.
What should the project manager do next?
Question 1052

A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do?
Question 1053

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected. What should the project manager do?
Question 1054

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.
What should the project manager do to handle this situation?
Question 1055

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component managed by an external vendor. How should the project manager address the team member's concern?
Question 1056

During the last iteration of a hybrid project., one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
Question 1057

A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
Question 1058

In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
Question 1059

After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.
What should the project manager do before the project kick-off meeting?
Question 1060

A company is starting a new agile project with a team that has expertise working on these kinds of projects. During the backlog refinement meeting, the team realizes that they are not completing the estimations because some key information is missing.
What should the project manager do?
Question