The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives.

The project runs into further delays as the project manager is ramping up on the project. The stakeholders are unhappy and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.
Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.
Answers
A.
Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.
B.
Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.
Answers
B.
Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.
C.
Socialize with the stakeholders to better understand their needs and reset expectations.
Answers
C.
Socialize with the stakeholders to better understand their needs and reset expectations.
D.
Continue to work on the project until the stakeholders and management come to a decision.
Answers
D.
Continue to work on the project until the stakeholders and management come to a decision.
Suggested answer: A