A project manager has been assigned to a new project. The project schedule is extremely short. During an iteration review meeting. the key stakeholder mentions that they are experiencing some inefficiencies in their work processes.
What should the project manager do?
A.
Perform a schedule impact analysis with the team.
B.
Ask the team to evaluate their process
C.
Review deliverables with the key stakeholder.
D.
Seek support from the project sponsor.