Question 1110 - PMP discussion
A project team is working remotely on a project with tight deadlines. In the middle of the project, a team member is replaced with an individual who is new to the company. The document repository is available to review, but since the project is quite complex it could take time to understand the details related to the new team member's responsibilities.
What should the project manager do?
A.
Assign tasks and provide contacts so the new team member can contact the appropriate resources for support.
B.
Ask the new team member to review the repository and schedule a meeting to provide details and tasks.
C.
Organize a social event to introduce the new team member to key stakeholders and the project team.
D.
Introduce the new team member to the project team and provide an explanation of the key themes.