In a daily standup, the project lead notices that one of the senior developers is reassigning some of the easy backlog items to other team members, arguing that it is more efficient for the senior developers to work on complex items. What should the project lead do?

A.
Include this practice in the next sprint review and discuss it with all of the team members.
Answers
A.
Include this practice in the next sprint review and discuss it with all of the team members.
B.
Ask the senior developer to stop assigning tasks because that's the scrum master's job.
Answers
B.
Ask the senior developer to stop assigning tasks because that's the scrum master's job.
C.
Support the senior developer's action and their authority over other team members.
Answers
C.
Support the senior developer's action and their authority over other team members.
D.
Include this practice in the next sprint retrospective and discuss it with all of the team members.
Answers
D.
Include this practice in the next sprint retrospective and discuss it with all of the team members.
Suggested answer: D