An organization is using a hybrid delivery approach for a complex project. In the iteration review, a subject matter expert (SME) informed the team that new legislation will be published in a few months.

What should the project manager do?

A.
Ask the SME to provide details after the retrospective.
Answers
A.
Ask the SME to provide details after the retrospective.
B.
Discuss the change in the next sprint planning.
Answers
B.
Discuss the change in the next sprint planning.
C.
Discuss the change in the next release planning.
Answers
C.
Discuss the change in the next release planning.
D.
Ask the SME to provide details in the next daily standup.
Answers
D.
Ask the SME to provide details in the next daily standup.
Suggested answer: B