ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1115 - PMP discussion

Report
Export

During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome.

Which method should the project manager use to assess and manage project risks?

A.
Influence diagrams
Answers
A.
Influence diagrams
B.
Sensitivity analysis
Answers
B.
Sensitivity analysis
C.
Decision tree analysis
Answers
C.
Decision tree analysis
D.
Monte Carlo analysis
Answers
D.
Monte Carlo analysis
Suggested answer: D
asked 23/09/2024
Amardeep Kumar
32 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first