Question 1115 - PMP discussion
During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome.
Which method should the project manager use to assess and manage project risks?
A.
Influence diagrams
B.
Sensitivity analysis
C.
Decision tree analysis
D.
Monte Carlo analysis