Question 1116 - PMP discussion
A key project team member had an accident and will be in the hospital for at least two months.
The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them.
What could the project manager have done to avoid this situation?
A.
Identified this risk and defined a risk response plan
B.
Assigned the backlog items to at least two of the team members
C.
Developed a knowledge transfer plan
D.
Reserved a contingency budget for external consultants