ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1116 - PMP discussion

Report
Export

A key project team member had an accident and will be in the hospital for at least two months.

The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them.

What could the project manager have done to avoid this situation?

A.
Identified this risk and defined a risk response plan
Answers
A.
Identified this risk and defined a risk response plan
B.
Assigned the backlog items to at least two of the team members
Answers
B.
Assigned the backlog items to at least two of the team members
C.
Developed a knowledge transfer plan
Answers
C.
Developed a knowledge transfer plan
D.
Reserved a contingency budget for external consultants
Answers
D.
Reserved a contingency budget for external consultants
Suggested answer: C
asked 23/09/2024
Kong Yew Kuen
38 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first