Question 1111

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.
What should the project manager do to demonstrate the capabilities of a servant leader?
Question 1112

There is an upcoming merger between a functional organization and an agile organization. The merger has necessitated that team members from both organizations brainstorm the effect this merger will have on critical compliance standards and the previous regulations for a project.
What should the project manager do in order to achieve this objective?
Question 1113

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?
Question 1114

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a subject matter expert (SME) informed the team that new legislation will be published in a few months.
What should the project manager do?
Question 1115

During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome.
Which method should the project manager use to assess and manage project risks?
Question 1116

A key project team member had an accident and will be in the hospital for at least two months.
The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them.
What could the project manager have done to avoid this situation?
Question 1117

A development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature.
What should the project manager do next?
Question 1118

Based on a new company policy, an aviation software project has been structured to use an agile approach. The project is subject to industry regulations, which require detailed tracking and archival of product changes.
What should the project manager use to understand the impact of compliance on this project?
Question 1119

A project manager is leading a program execution and has challenges, because a project team waits for every decision to be made by the project manager. The progress of the team is slow because the project manager is the bottleneck. Upon assessing the situation, the project manager realized that the team members can handle the work on their own.
What should the project manager do?
Question 1120

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.
Which tool should the project manager use for this purpose?