A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.

Which three actions should the project manager do? (Choose three.)

A.
Identify in the iteration planning the acceptance criteria that meet quality standards.
Answers
A.
Identify in the iteration planning the acceptance criteria that meet quality standards.
B.
Identify the acceptance criteria during the retrospective that meet the quality standards.
Answers
B.
Identify the acceptance criteria during the retrospective that meet the quality standards.
C.
Analyze the lessons learned to determine appropriate testing metrics in quality standards.
Answers
C.
Analyze the lessons learned to determine appropriate testing metrics in quality standards.
D.
Incorporate performance metrics on the verified deliverables according to quality standards.
Answers
D.
Incorporate performance metrics on the verified deliverables according to quality standards.
E.
Perform a risk analysis to determine the impact of not complying with quality standards.
Answers
E.
Perform a risk analysis to determine the impact of not complying with quality standards.
Suggested answer: A, C, D