The project team has onboarded members from all over the world and will now work virtually to create project deliverables. There are both language and time zone challenges with this project team, but each team member is an expert in their trade.

What should the project manager do first to address the challenges?

A.
Schedule meetings at a time when all members can attend based on the time zones.
Answers
A.
Schedule meetings at a time when all members can attend based on the time zones.
B.
Engage with human resources (HR) to determine if some team members may be relocated.
Answers
B.
Engage with human resources (HR) to determine if some team members may be relocated.
C.
Review the communications management plan to assign resources for a facilitator.
Answers
C.
Review the communications management plan to assign resources for a facilitator.
D.
Investigate alternatives for virtual meeting times and written communication methods.
Answers
D.
Investigate alternatives for virtual meeting times and written communication methods.
Suggested answer: D