A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

A.
Communicate the project details to the stakeholders.
Answers
A.
Communicate the project details to the stakeholders.
B.
Introduce a separate stakeholder engagement meeting.
Answers
B.
Introduce a separate stakeholder engagement meeting.
C.
Analyze the communication needs of the stakeholders.
Answers
C.
Analyze the communication needs of the stakeholders.
D.
Communicate progress more frequently to the stakeholders.
Answers
D.
Communicate progress more frequently to the stakeholders.
Suggested answer: C