A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.
What should the project manager do?
A.
Communicate the project details to the stakeholders.
B.
Introduce a separate stakeholder engagement meeting.
C.
Analyze the communication needs of the stakeholders.
D.
Communicate progress more frequently to the stakeholders.