A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.
Send a gentle reminder to the technical service team.
Answers
A.
Send a gentle reminder to the technical service team.
B.
Use interpersonal skills to expedite the issue.
Answers
B.
Use interpersonal skills to expedite the issue.
C.
Update the issue log with the status and priority.
Answers
C.
Update the issue log with the status and priority.
D.
Issue a formal warning to the technical service team.
Answers
D.
Issue a formal warning to the technical service team.
Suggested answer: B