A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource's refusal?
A.
Speak with their colleague.
B.
Communicate with their supervisor.
C.
Speak directly with the resource.
D.
Organize a team meeting.