An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
A.
Meet with the project team to develop a proper resolution to the issue.
B.
Request approval from the project sponsor to add more resources
C.
Prepare documentation to explain the issue and communicate accordingly.
D.
Update the project artifacts to reflect the new deadlines reported.
Your answer: