Question 1144 - PMP discussion
A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client's organization on the email.
What should the project manager do?
A.
Contact the other manager and ask them to delete the email.
B.
Inform the client and their supervisor about the mistake.
C.
Wait for the client's feedback regarding the report.
D.
Resend the email to the client, excluding the other manager.