A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?
A.
Disregard the request since the project scope is finalized
B.
Adjust the project schedule to accommodate the new project scope requests.
C.
Create a change request for the change control board (CCB) to review.
D.
Update the project team about the change request.