Question 1146 - PMP discussion

Report
Export

A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?

A.
Disregard the request since the project scope is finalized
Answers
A.
Disregard the request since the project scope is finalized
B.
Adjust the project schedule to accommodate the new project scope requests.
Answers
B.
Adjust the project schedule to accommodate the new project scope requests.
C.
Create a change request for the change control board (CCB) to review.
Answers
C.
Create a change request for the change control board (CCB) to review.
D.
Update the project team about the change request.
Answers
D.
Update the project team about the change request.
Suggested answer: C