A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.
Review the new requirements with the compliance department to determine if a change request is needed
Answers
A.
Review the new requirements with the compliance department to determine if a change request is needed
B.
Proceed with the defined project requirements and delay implementing the new requirements
Answers
B.
Proceed with the defined project requirements and delay implementing the new requirements
C.
Add the new requirements to the project scope immediately since they are mandatory changes
Answers
C.
Add the new requirements to the project scope immediately since they are mandatory changes
D.
Ignore the new requirements as the current budget and schedule do not allow for any changes
Answers
D.
Ignore the new requirements as the current budget and schedule do not allow for any changes
Suggested answer: A