A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
A.
Extract this from the project risk register tracking tool and issues log
B.
Refer the sponsor to the contract document
C.
Organize a stakeholder meeting to brainstorm on general project risks
D.
Share the annual report with the sponsor