A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
A.
Request for information
B.
Scope statement
C.
Risk register
D.
Issue log