A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

A.
Request for information
Answers
A.
Request for information
B.
Scope statement
Answers
B.
Scope statement
C.
Risk register
Answers
C.
Risk register
D.
Issue log
Answers
D.
Issue log
Suggested answer: C