A project manager learns that the performance of a high-performing project team member is deteriorating. This team member is a key member of the project.
Which action should the project manager take to motivate and enhance the project team member's performance?
A.
Assign the project team member to more challenging tasks.
B.
Recognize the project team member in a leadership forum.
C.
Mentor the project team member by providing step-by-step guidance.
D.
Discuss the issue with the team member and work on an agreed option.