A project is being planned to deliver a proof of concept to evaluate technology compatibilities.

The business and project stakeholders are having difficulty agreeing on what should be included in the final product.

What should the project manager do?

A.
Include all stakeholders in the creation of the project charter.
Answers
A.
Include all stakeholders in the creation of the project charter.
B.
Determine a clear distinction between business and technology benefits.
Answers
B.
Determine a clear distinction between business and technology benefits.
C.
Include the technology suppliers in the creation of the business case.
Answers
C.
Include the technology suppliers in the creation of the business case.
D.
Determine the root cause of their inability to determine the project scope.
Answers
D.
Determine the root cause of their inability to determine the project scope.
Suggested answer: D