ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1165 - PMP discussion

Report
Export

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

A.
Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
Answers
A.
Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
B.
Continue working with the predictive approach to deliver the value at the end of the project.
Answers
B.
Continue working with the predictive approach to deliver the value at the end of the project.
C.
Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
Answers
C.
Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
D.
Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.
Answers
D.
Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.
Suggested answer: D
asked 23/09/2024
Hristo Slaveev
25 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first