A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A.
Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
B.
Continue working with the predictive approach to deliver the value at the end of the project.
C.
Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
D.
Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.