Question 1166 - PMP discussion
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented. This may require a significant change in the technical architecture and an additional release.
What should the project lead do first?
A.
Discuss with the solution architect
B.
Discuss with the product owner
C.
Discuss with the technical lead
D.
Discuss with the development team