An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?

A.
Engage an external consultancy to assemble supporting documents and coordinate the knowledge transfer.
Answers
A.
Engage an external consultancy to assemble supporting documents and coordinate the knowledge transfer.
B.
Propose a workshop with the operations team to outline all requirements of the new software and how to properly support it.
Answers
B.
Propose a workshop with the operations team to outline all requirements of the new software and how to properly support it.
C.
Ensure the operations team has representation in the planning and review meetings and that there are support requirements in the backlog.
Answers
C.
Ensure the operations team has representation in the planning and review meetings and that there are support requirements in the backlog.
D.
Create and prioritize a support manual on the product backlog to ensure adequate knowledge transfer.
Answers
D.
Create and prioritize a support manual on the product backlog to ensure adequate knowledge transfer.
Suggested answer: C