An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?
A.
Assess consolidated project plans for dependencies, gaps, and continued business value
B.
Delegate the review of dependencies to the project sponsor and resource manager
C.
Schedule a daily interproject review to track the progress of each project plan and their dependencies
D.
Ask the project management office (PMO) to review the project plan dependencies