In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time.

What should the project manager do first?

A.
Assess the schedule and update the risk register.
Answers
A.
Assess the schedule and update the risk register.
B.
Report the delay to all other subcontractors.
Answers
B.
Report the delay to all other subcontractors.
C.
Change the milestones and sequence of work.
Answers
C.
Change the milestones and sequence of work.
D.
Escalate to senior management and the stakeholders.
Answers
D.
Escalate to senior management and the stakeholders.
Suggested answer: A