Question 1173 - PMP discussion
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach. Recently, the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large, complex project with the same group of stakeholders.
What should the project manager do?
A.
Continue to use the predictive approach in the new project since it is the approach the stakeholders are familiar with using.
B.
Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use.
C.
Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach.
D.
Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project.
Your answer: