List of questions
Related questions
Question 1174 - PMP discussion
A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity What should the team member do?
A.
Inform the scrum master so that the change can be discussed directly with the stakeholder.
B.
Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity
C.
Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.
D.
Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).
Your answer:
0 comments
Sorted by
Leave a comment first