Question 1179 - PMP discussion
A project manager is preparing the business case for a project in a not for profit organization. The project manager justifies the cost of the project to a group of sponsors.
Which benefits realization metric should the project manager use?
A.
Budget at Completion (BAC)
B.
Payback period
C.
Total value of ownership
D.
Return of investment (ROI)
Your answer: