Question 1193 - PMP discussion

Report
Export

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

A.
Delegate certain authorities and share information to allow fair decision-making.
Answers
A.
Delegate certain authorities and share information to allow fair decision-making.
B.
Delegate most authorities and share information to allow fair decision-making.
Answers
B.
Delegate most authorities and share information to allow fair decision-making.
C.
Delegate most authorities and control the authority by withholding important information.
Answers
C.
Delegate most authorities and control the authority by withholding important information.
D.
Delegate certain authorities and control the authority by withholding important information.
Answers
D.
Delegate certain authorities and control the authority by withholding important information.
Suggested answer: A
asked 23/09/2024
Ghazi Khan