Question 1194 - PMP discussion

Report
Export

For some time now, doubts have been raised about who is responsible for delivering a key benefit of a project. What should the project manager do next?

A.
Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit.
Answers
A.
Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit.
B.
Understand the context of the situation and escalate the problem to the steering committee.
Answers
B.
Understand the context of the situation and escalate the problem to the steering committee.
C.
Document the risk in the risk register and generate the risk responses and their respective associated plans.
Answers
C.
Document the risk in the risk register and generate the risk responses and their respective associated plans.
D.
Meet with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit.
Answers
D.
Meet with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit.
Suggested answer: A