A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the night opportunity to include daily standup meetings. The project team has never used such tools, and a few members are challenging the decision.

What should the project manager do in this situation?

A.
Update the project schedule to consider a daily standup as part of the project design phase
Answers
A.
Update the project schedule to consider a daily standup as part of the project design phase
B.
Engage an external vendor to perform the design phase under an iterative approach
Answers
B.
Engage an external vendor to perform the design phase under an iterative approach
C.
Request that new team members familiar with iterative approaches be assigned to this project
Answers
C.
Request that new team members familiar with iterative approaches be assigned to this project
D.
Define the ground rules, responsibilities, and conflict management strategies
Answers
D.
Define the ground rules, responsibilities, and conflict management strategies
Suggested answer: D