Question 1196 - PMP discussion

Report
Export

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

A.
Perform a gap analysis on renting in each of the locations.
Answers
A.
Perform a gap analysis on renting in each of the locations.
B.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
Answers
B.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
C.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
Answers
C.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
D.
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
Answers
D.
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
Suggested answer: B
asked 23/09/2024
Antonio Carlos Figueiredo Junior
50 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first