Question 1196 - PMP discussion
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A.
Perform a gap analysis on renting in each of the locations.
B.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
C.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
D.
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
Your answer: