ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1197 - PMP discussion

Report
Export

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee:

Actual progress = 2 units

Planned progress = 3 units

Actual cost (AC) = 2 units

Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.
The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted
Answers
A.
The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted
B.
The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken
Answers
B.
The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken
C.
The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
Answers
C.
The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
D.
The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
Answers
D.
The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
Suggested answer: C
asked 23/09/2024
Piotr Szwajkowski
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first