A project manager is reviewing the status of a large project with team members in different countries. Through the status review. the project manager notices that one team is consistently behind schedule and their work often needs to be corrected.

What should the project manager do to improve the quality of this team's work?

A.
Guide all team members and bring in external consultants to complete the work.
Answers
A.
Guide all team members and bring in external consultants to complete the work.
B.
Review the issue with the project sponsor and work to reduce the scope for that team.
Answers
B.
Review the issue with the project sponsor and work to reduce the scope for that team.
C.
Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.
Answers
C.
Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.
D.
Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.
Answers
D.
Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.
Suggested answer: D