ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 47

Question list
Search
Search

Which of the following is an input to the Direct and Manage Project Execution process?

A.
Approved change requests
A.
Approved change requests
Answers
B.
Approved contract documentation
B.
Approved contract documentation
Answers
C.
Work performance information
C.
Work performance information
Answers
D.
Rejected change requests
D.
Rejected change requests
Answers
Suggested answer: A

Which of the following factors is lowest at the start of the project?

A.
Cost of changes
A.
Cost of changes
Answers
B.
Stakeholder influences
B.
Stakeholder influences
Answers
C.
Risk
C.
Risk
Answers
D.
Uncertainty
D.
Uncertainty
Answers
Suggested answer: A

In which domain of project management would a Pareto chart provide useful information?

A.
Project Scope Management
A.
Project Scope Management
Answers
B.
Project Time Management
B.
Project Time Management
Answers
C.
Project Communications Management
C.
Project Communications Management
Answers
D.
Project Quality Management
D.
Project Quality Management
Answers
Suggested answer: D

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

A.
Conduct Procurements.
A.
Conduct Procurements.
Answers
B.
Close Procurements.
B.
Close Procurements.
Answers
C.
Administer Procurements,
C.
Administer Procurements,
Answers
D.
Plan Procurements.
D.
Plan Procurements.
Answers
Suggested answer: C

In which process might a project manager use risk reassessment as a tool and technique?

A.
Perform Qualitative Risk Analysis
A.
Perform Qualitative Risk Analysis
Answers
B.
Monitor and Control Risk
B.
Monitor and Control Risk
Answers
C.
Monitor and Control Project Work
C.
Monitor and Control Project Work
Answers
D.
Plan Risk Responses
D.
Plan Risk Responses
Answers
Suggested answer: B

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.
Cost-reimbursable
A.
Cost-reimbursable
Answers
B.
Time and material
B.
Time and material
Answers
C.
Fixed price or lump-sum
C.
Fixed price or lump-sum
Answers
D.
Cost-plus-fixed-fee
D.
Cost-plus-fixed-fee
Answers
Suggested answer: C

What risk technique is used to quantify the probability and impact of risks on project objectives?

A.
Expert judgment
A.
Expert judgment
Answers
B.
Risk registry
B.
Risk registry
Answers
C.
Risk response planning
C.
Risk response planning
Answers
D.
Interviewing
D.
Interviewing
Answers
Suggested answer: D

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A.
WBS directory
A.
WBS directory
Answers
B.
Activity list
B.
Activity list
Answers
C.
WBS
C.
WBS
Answers
D.
Project schedule
D.
Project schedule
Answers
Suggested answer: C

Which process occurs within the Monitoring and Controlling Process Group?

A.
Control Costs
A.
Control Costs
Answers
B.
Plan Quality
B.
Plan Quality
Answers
C.
Perform Quantitative Risk Analysis
C.
Perform Quantitative Risk Analysis
Answers
D.
Determine Budget
D.
Determine Budget
Answers
Suggested answer: A

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.
Perform Quality Control
A.
Perform Quality Control
Answers
B.
Quality Metrics
B.
Quality Metrics
Answers
C.
Perform Quality Assurance
C.
Perform Quality Assurance
Answers
D.
Plan Quality
D.
Plan Quality
Answers
Suggested answer: C
Total 908 questions
Go to page: of 91