Question 451

Which type of chart is a graphic representation of a process showing the relationships among process steps?
Question 452

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Question 453

Which tool and technique is used in Conduct Procurements?
Question 454

What provides information regarding the ways people, teams, and organizational units behave?
Question 455

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Question 456

What causes replanning of the project scope?
Question 457

Which of the following is an output of the Distribute Information process?
Question 458

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Question 459

The project scope statement and resource calendars are inputs to which Project Time Management process?
Question 460

Which process determines the risks that might affect the project?