Which type of chart is a graphic representation of a process showing the relationships among process steps?

A.
Control
A.
Control
Answers
B.
Bar
B.
Bar
Answers
C.
Flow
C.
Flow
Answers
D.
Pareto
D.
Pareto
Answers
Suggested answer: C

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

A.
1
A.
1
Answers
B.
0.4
B.
0.4
Answers
C.
0.5
C.
0.5
Answers
D.
0.8
D.
0.8
Answers
Suggested answer: D

Which tool and technique is used in Conduct Procurements?

A.
Teaming agreements
A.
Teaming agreements
Answers
B.
Expert judgment
B.
Expert judgment
Answers
C.
Bidder conferences
C.
Bidder conferences
Answers
D.
Contract types
D.
Contract types
Answers
Suggested answer: C

What provides information regarding the ways people, teams, and organizational units behave?

A.
Organizational chart
A.
Organizational chart
Answers
B.
Organizational theory
B.
Organizational theory
Answers
C.
Organizational structure
C.
Organizational structure
Answers
D.
Organizational behavior
D.
Organizational behavior
Answers
Suggested answer: B

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.
Organizational breakdown structure (OBS)
A.
Organizational breakdown structure (OBS)
Answers
B.
Work performance information
B.
Work performance information
Answers
C.
Work package
C.
Work package
Answers
D.
Work breakdown structure (WBS)
D.
Work breakdown structure (WBS)
Answers
Suggested answer: D

What causes replanning of the project scope?

A.
Project document updates
A.
Project document updates
Answers
B.
Project scope statement changes
B.
Project scope statement changes
Answers
C.
Variance analysis
C.
Variance analysis
Answers
D.
Change requests
D.
Change requests
Answers
Suggested answer: D

Which of the following is an output of the Distribute Information process?

A.
Project calendar
A.
Project calendar
Answers
B.
Communications management plan
B.
Communications management plan
Answers
C.
Organizational process assets updates
C.
Organizational process assets updates
Answers
D.
Project document updates
D.
Project document updates
Answers
Suggested answer: C

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

A.
Team meetings
A.
Team meetings
Answers
B.
Subcontracting teams
B.
Subcontracting teams
Answers
C.
Virtual teams
C.
Virtual teams
Answers
D.
Teamwork
D.
Teamwork
Answers
Suggested answer: D

The project scope statement and resource calendars are inputs to which Project Time Management process?

A.
Sequence Activities
A.
Sequence Activities
Answers
B.
Estimate Activity Resources
B.
Estimate Activity Resources
Answers
C.
Develop Schedule
C.
Develop Schedule
Answers
D.
Control Schedule
D.
Control Schedule
Answers
Suggested answer: C

Which process determines the risks that might affect the project?

A.
Perform Qualitative Risk Analysis
A.
Perform Qualitative Risk Analysis
Answers
B.
Identify Risks
B.
Identify Risks
Answers
C.
Plan Risk Management
C.
Plan Risk Management
Answers
D.
Perform Quantitative Risk Analysis
D.
Perform Quantitative Risk Analysis
Answers
Suggested answer: B
Total 908 questions
Go to page: of 91