Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.
Estimate Costs
A.
Estimate Costs
Answers
B.
Estimate Activity Resources
B.
Estimate Activity Resources
Answers
C.
Control Costs
C.
Control Costs
Answers
D.
Determine Budget
D.
Determine Budget
Answers
Suggested answer: D

Plan Risk Management is the process of defining how to:

A.
Communicate identified risks to the project stakeholders.
A.
Communicate identified risks to the project stakeholders.
Answers
B.
Conduct risk management activities for a project.
B.
Conduct risk management activities for a project.
Answers
C.
Analyze the impact a specific risk may have on the project.
C.
Analyze the impact a specific risk may have on the project.
Answers
D.
Address unexpected risks that may occur during a project.
D.
Address unexpected risks that may occur during a project.
Answers
Suggested answer: B

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.
One
A.
One
Answers
B.
Five
B.
Five
Answers
C.
Six
C.
Six
Answers
D.
Seven
D.
Seven
Answers
Suggested answer: C

The CPI is .92, and the EV is US$172,500.

What is the actual cost of the project?

A.
US$158,700
A.
US$158,700
Answers
B.
US$172,500
B.
US$172,500
Answers
C.
US$187,500
C.
US$187,500
Answers
D.
US$245,600
D.
US$245,600
Answers
Suggested answer: C

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

A.
Control chart
A.
Control chart
Answers
B.
Earned value
B.
Earned value
Answers
C.
Variance
C.
Variance
Answers
D.
Trend
D.
Trend
Answers
Suggested answer: D

Which is one of the major outputs of Sequence Activities?

A.
Responsibility assignment matrix (RAM)
A.
Responsibility assignment matrix (RAM)
Answers
B.
Work breakdown structure (WBS) update
B.
Work breakdown structure (WBS) update
Answers
C.
Project schedule network diagram
C.
Project schedule network diagram
Answers
D.
Mandatory dependencies list
D.
Mandatory dependencies list
Answers
Suggested answer: C

The Human Resource Management processes are:

A.
Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
A.
Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.
Answers
B.
Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
B.
Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.
Answers
C.
Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
C.
Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.
Answers
D.
Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.
D.
Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.
Answers
Suggested answer: A

What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

A.
Organizational process assets
A.
Organizational process assets
Answers
B.
Enterprise environmental factors
B.
Enterprise environmental factors
Answers
C.
Project management processes
C.
Project management processes
Answers
D.
Project scope management plan
D.
Project scope management plan
Answers
Suggested answer: A

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.
Budget plan
A.
Budget plan
Answers
B.
Resource plan
B.
Resource plan
Answers
C.
Scope plan
C.
Scope plan
Answers
D.
Strategic plan
D.
Strategic plan
Answers
Suggested answer: D

When does Monitor and Control Risks occur?

A.
At project initiation
A.
At project initiation
Answers
B.
During work performance analysis
B.
During work performance analysis
Answers
C.
Throughout the life of the project
C.
Throughout the life of the project
Answers
D.
At project milestones
D.
At project milestones
Answers
Suggested answer: C