What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

A.
Decomposition
A.
Decomposition
Answers
B.
Benchmarking
B.
Benchmarking
Answers
C.
Inspection
C.
Inspection
Answers
D.
Checklist analysis
D.
Checklist analysis
Answers
Suggested answer: C

To which process is work performance information an input?

A.
Administer Procurements
A.
Administer Procurements
Answers
B.
Direct and Manage Project Execution
B.
Direct and Manage Project Execution
Answers
C.
Create WBS
C.
Create WBS
Answers
D.
Perform Qualitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Answers
Suggested answer: A

Which defines the portion of work included in a contract for items being purchased or acquired?

A.
Procurement management plan
A.
Procurement management plan
Answers
B.
Evaluation criteria
B.
Evaluation criteria
Answers
C.
Work breakdown structure
C.
Work breakdown structure
Answers
D.
Procurement statement of work
D.
Procurement statement of work
Answers
Suggested answer: D

Cost baseline is an output of which of the following processes?

A.
Control Costs
A.
Control Costs
Answers
B.
Determine Budget
B.
Determine Budget
Answers
C.
Estimate Costs
C.
Estimate Costs
Answers
D.
Estimate Activity Resources
D.
Estimate Activity Resources
Answers
Suggested answer: B

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.
The Delphi technique
A.
The Delphi technique
Answers
B.
Nominal group technique
B.
Nominal group technique
Answers
C.
Affinity diagram
C.
Affinity diagram
Answers
D.
Brainstorming
D.
Brainstorming
Answers
Suggested answer: A

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

A.
Final phase of the project
A.
Final phase of the project
Answers
B.
Start of the project
B.
Start of the project
Answers
C.
End of the project
C.
End of the project
Answers
D.
Midpoint of the project
D.
Midpoint of the project
Answers
Suggested answer: B

What type of project structure is a hierarchically organized depiction of the resources by type?

A.
Organizational breakdown structure (OBS)
A.
Organizational breakdown structure (OBS)
Answers
B.
Resource breakdown structure (RBS)
B.
Resource breakdown structure (RBS)
Answers
C.
Work breakdown structure (WBS)
C.
Work breakdown structure (WBS)
Answers
D.
Project breakdown structure (PBS)
D.
Project breakdown structure (PBS)
Answers
Suggested answer: B

When can pre-assignment of project team members occur?

A.
When the project uses capital expenditures
A.
When the project uses capital expenditures
Answers
B.
When the required staff can be acquired from outside sources
B.
When the required staff can be acquired from outside sources
Answers
C.
When the project would be ignored due to travel expenses
C.
When the project would be ignored due to travel expenses
Answers
D.
When the project is the result of specific people being promised as part of a competitive proposal
D.
When the project is the result of specific people being promised as part of a competitive proposal
Answers
Suggested answer: D

An output of the Create WBS process is:

A.
Scope baseline.
A.
Scope baseline.
Answers
B.
Project scope statement.
B.
Project scope statement.
Answers
C.
Organizational process assets.
C.
Organizational process assets.
Answers
D.
Requirements traceability matrix.
D.
Requirements traceability matrix.
Answers
Suggested answer: A

Change requests are an output from which Project Integration Management process?

A.
Direct and Manage Project Execution
A.
Direct and Manage Project Execution
Answers
B.
Develop Project Management Plan
B.
Develop Project Management Plan
Answers
C.
Close Project
C.
Close Project
Answers
D.
Develop Project Charter
D.
Develop Project Charter
Answers
Suggested answer: A